The Targeted Actions to Increase London's Housing Supply: Supporting Council's Pledge for 47,000 units by 2031 identifies the tracking and reporting methods associated with different categories of housing units in the development pipeline.
Development Pipeline Process Overview
The development pipeline process highlights a timeline that shows the average time for land to progress through the land development process. The entire process is linear and can take up to 10 years to complete.
| New Units Year-to-Date | Provincial Pledge Total New units |
| 5,412 | 56,846 |
New housing units in permits issued by the Building Division (As of April 30)
| Units (2026 YTD) | Units in 2025 | Units in 2024 |
| 554 | 5,462 | 3,700 |
| Category | Under Construction | 2022 | 2023 | 2024 | 2025 | 2026 YTD | Total |
| Housing Starts | 2,495 | 1,534 | 3,089 | 2,553 | 1,812 | 11,483 | |
| Additional Residential Units (ARUs) and Conversions to Residential | 224 | 281 | 487 | 664 | 83* | 1,739 | |
| Long-Term Care Beds | 0 | 256 | 0 | N/A | N/A | 256 | |
| Postsecondary Student Beds | 0 | 0 | 0 | 796 | N/A | 796 | |
| Congregate Retirement Home Suites | 0 | 0 | 147 | N/A | N/A | 147 | |
| Pre 2022 Housing Starts | 591 | 412 | 195 | 832 | 804 | 91 | 2,925 |
| Total new housing units | 591 | 3,131 | 2,266 | 4,555 | 4,817 | 1,986 | 17,346 |
*Includes additional residential units and office-to-residential conversions reported up to the period ending on March 31.
CMHC defines a housing start as the beginning of construction work on the building where the dwelling unit will be located. Due to the delay between permit issuance and a CMHC housing start, the number of permits issued and the number of housing starts will not match. Preliminary work on a housing construction site may occur before or after a permit building permit is issued. Learn more about how the Province of Ontario is tracking housing supply progress.
Visit Canada Mortgage and Housing Corporation (CHMC)to find housing market, data and research reports and their housing market information portal offers free, easy-to-use access to the latest housing market data for Canada.