Pottersburg Sanitary Trunk Sewer Environmental Assessment

Background

The existing Pottersburg Creek Trunk Sanitary Sewer crosses the Pottersburg Creek several times at a shallow depth with segments of the sewer in poor condition. Additionally, portions of the existing Pottersburg Creek Trunk Sanitary Sewer are located on private property, limiting access to the sewer. The existing sewer is in need of rehabilitation or replacement, however, due to its alignment, localized rehabilitation is challenging. Subsequently, the City has retained GM Blueplan Engineering Ltd., as the Consultant to carry out a Schedule ‘B’ Municipal Class Environmental Assessment (EA) study to identify the preferred Pottersburg Creek Trunk Sanitary Sewer Realignment.

Watch the Environmental Assessment  Public Information Centre Presentations, and provide your Input

Current status

A virtual Public Information Centre (PIC) has been posted to the City's Get Involved page

Interested parties are invited to ask questions and provide input by either contacting the project manager or submitting a question or comment through the survey available on the Get Involved page. A paper copy of the survey has been mailed to nearby residents and business owners.

Study area

This study area for this project is within the Argyle neighbourhood in the City of London, north of Dundas Street between First Street and Clarke Road. This Sanitary Trunk Sewer will be constructed over a number of years, with a number of phases which will be identified further along in the detailed design process.

Image
A map of the Pottersburg Creek Truck Sanitary Sewer Environmental Assessment Area. For more information, please contact Alex Corpodean at acorpodean@london.ca or by calling 519-661-2489 x 8437

A map of the Pottersburg Creek Truck Sanitary Sewer Environmental Assessment Area. 


Contact us

If you require documents in an alternate format or have questions about this project, please contact Alex Corpodean, C. Tech, PACP at acorpodean@london.ca or by phone at 519-661-2489 x 8437.

With the exception of personal information, all comments will become part of the public record of the study.

The study is being conducted according to the requirements of the Municipal Class Environmental Assessment, which is a planning process approved under Ontario’s Environmental Assessment Act.

Project Timeline

January 2020: Notice of Commencement

A Notice of Commencement was completed and issued in January 2020.

April 2021: Host Public Information Centre

A Public Information Centre is being planned for April 2021. This would be an opportunity for the City to obtain public feedback on the proposed projects and expected impacts. 

June 2021: Submit Civic Works Committee Report to Council

A Civic Works Committee Report to Council is being planned recommending the findings of the Environmental Assessment.

June 2021: Final study document prepared and posted for review

The final study document would be prepared in June 2021 and posted for a 30 day public review and comment period.

July 2021: Finalize study document

The final study document would be completed in winter 2021.